Replacing Modems
If we supply you with a replacement modem, for example to upgrade from 2G to 4G comms, please follow the procedure below:
- Ensure the meter is fully turned off before replacing the modem.
- For Emlite meters, the modem is situated at the top of top of the meter and can be removed by loosening the screw(s) holding it in place.
- For Elster A1140 meters, the modem is situated under the bottom cover, which is held in place by two screws, left and right.
-
Please record the following information:
-
Serial number of the modem, which can be found on the rear of the modem.
- Serial number of the meter that you are fitting the modem on to.
Please provide the information above to the staff at support@juggle.energy who will be able to update the records in Juggle.
Installing New ASL Meters
The basic meter installation is as for any energy meter - the range of meters are straightforward electrically and any competent electrician will be able to complete the installation.
If Juggle Energy have provided you with the meter (with a modem and SIM included) then you only need to provide the following information to Juggle Energy Ltd to allow this to be set up:
- If this is a replacement meter, the existing "emig ID" of the meter.
- The serial number of the meter (we will hold records of the modem & SIM details)
- The "name" of the site / property and the full postal address
- For PV systems, the maximum AC power rating of the connected inverter(s)
Obtaining a good Mobile Signal